County commissioners discuss ongoing projects

County Engineer, Stuart Porter, was present to discuss the guardrail replacement project on the Waconda Lake Causeway during Monday mornings Mitchell County Commissioners meeting. He had a program document for the decision aspect of the project. This second phase of the guardrail project is roughly twice the size as the first phase. He said the consultant design contract is due in Feb. of 2023 and he expects the work to be completed sometime in 2025. The total cost of the project is $2,259,712. Mitchell County’s contribution will be $360,000.